Vietnam Industrial Electricity Tariffs 2026: Rates from November 1 and New Peak Hours

Vietnam industrial electricity tariffs 2026

Vietnam industrial electricity tariffs 2026 were revised with effect from November 1, 2026, under Decision No. 2892/QĐ-BCT. Decision No. 963/QĐ-BCT establishes a new peak-hour period of 17:30–22:30, Monday through Saturday. However, the effective date of the revised tariffs and the date on which a customer’s meter is reconfigured to the new time-of-use schedule may not coincide. Factories should confirm both before recalculating their electricity costs.

Even with the same total electricity consumption, a factory operating mainly during daytime hours may be affected differently from one operating until 22:00. A reliable assessment requires comparing electricity bills with time-resolved load profiles, rather than relying solely on the average electricity price.

1. Industrial electricity tariffs effective November 1, 2026

On October 31, 2026, the Ministry of Industry and Trade (MOIT) issued Decision No. 2892/QĐ-BCT, setting electricity tariffs applicable from November 1, 2026. Vietnam Electricity (EVN) also announced an average retail electricity price of VND 2,159.9037/kWh, representing a 2% reduction from the previous level. This average is not the rate charged for every kilowatt-hour consumed by every factory.

Retail electricity tariffs for industrial production

Supply voltage Normal hours Off-peak hours Peak hours
220 kV and above 1,771 1,101 3,110
Above 35 kV to below 220 kV 1,792 1,123 3,218
Above 1 kV to 35 kV 1,814 1,166 3,348
Up to 1 kV 1,966 1,274 3,586

Unit: VND/kWh, excluding value-added tax (VAT). Figures are drawn from the “Retail Electricity Tariffs for Industrial Production” category in the Appendix to Decision No. 2892/QĐ-BCT. They do not supersede other tariffs applicable to electricity retailers or special contractual arrangements in industrial parks.

Sources for cross-checking: EVN – Announcement of the electricity price adjustment effective November 1, 2026; Decision No. 2892/QĐ-BCT and its electricity tariff appendix.

For customers subject to a three-rate time-of-use (TOU) tariff, the electricity bill depends on the applicable tariff category, the supply voltage at the metering point, and the electricity consumed during each time period. Under Clause 3, Article 5 of Circular No. 60/2025/TT-BCT, mandatory application includes production and commercial customers supplied through a dedicated transformer rated at 25 kVA or higher, or whose average monthly consumption is at least 2,000 kWh over three consecutive months, as well as certain electricity retailers specified in the same provision.

2. How have peak electricity hours changed?

Decision No. 963/QĐ-BCT, dated April 22, 2026, specifies a new peak period of 17:30–22:30, Monday through Saturday, replacing the previous split peak periods in the morning and evening. From Monday through Saturday, the total remains five peak hours per day. What changes is when those hours occur, not the total number of peak hours.

Visual comparison of daily time-of-use periods

Monday–Saturday: 24-hour schedule

Previous time-of-use schedule

Peak: 09:30–11:30 and 17:00–20:00 · Off-peak: 22:00–04:00.

Schedule prescribed by Decision No. 963/QĐ-BCT

Peak: 17:30–22:30 · Off-peak: 00:00–06:00.

Peak   Normal   Off-peak

This chart compares the defined time-of-use periods only. It does not confirm that any particular meter has been reconfigured. Neither schedule includes peak hours on Sundays.

Time-of-use comparison for checking electricity bills

Time-of-use category Before the change Under Decision No. 963
Peak 09:30–11:30; 17:00–20:00 17:30–22:30
Off-peak 22:00–04:00 the following day 00:00–06:00
Normal All remaining hours 06:00–17:30; 22:30–24:00

The comparison above applies Monday through Saturday. Under Decision No. 963, Sundays have off-peak hours from 00:00 to 06:00 and normal hours from 06:00 to 24:00.

Are the new peak hours already reflected in electricity bills?

It cannot be assumed that every factory has been billed under the new time-of-use schedule since November 1, 2026. Three dates must be distinguished: Decision No. 963 took effect on April 22, 2026; the tariffs under Decision No. 2892 apply from November 1, 2026; and each customer’s meter must be reconfigured in accordance with the transitional provisions and the electricity supplier’s implementation plan.

According to the guidance in Document No. 1026/ĐL-TTD&HTĐ dated April 24, 2026, the transitional provisions of Circular No. 60/2025/TT-BCT link implementation of the new time-of-use schedule to an adjustment in the average retail electricity price. EVN announced a price adjustment effective November 1, 2026. However, on October 20, 2026, MOIT also published a draft amendment to Decision No. 14/2025/QĐ-TTg to refine the implementation framework. As of November 2, 2026, no verified basis was available for stating that all meters would be reconfigured on the same date. Businesses should verify the regulations in force, notices issued by their electricity supplier, and the configuration date at their metering point before calculating any impact on their bills.

Under Clause 2, Article 5 of Circular No. 60/2025/TT-BCT, reconfiguration of meters for the new time-of-use periods must be completed within 90 days from the date the new schedule is applied. During the transition, meters that have not yet been reconfigured continue to use the previously applicable schedule. This 90-day period should not automatically be counted from April 22, 2026.

What should factories do? Ask the electricity supplier to confirm the time-of-use schedule currently programmed into the meter, the expected changeover date, and how the applicable schedule will be shown on electricity bills. If electricity is purchased through an industrial-park retailer, also review the contract terms and the tariff category actually applied.

Sources: MOIT – Decision No. 963/QĐ-BCT; Circular No. 60/2025/TT-BCT; Electricity Regulatory Authority – Document No. 1026/ĐL-TTD&HTĐ; Draft amendment dossier published October 20, 2026.

3. How could factory electricity costs change?

The new schedule may shift some electricity consumption from peak to normal hours, or vice versa. The financial impact depends on the actual load profile, production shifts, and whether the meter has been reconfigured.

Illustrative example: 1,000 kWh consumed at two different times

Assume a factory is billed under the above 1 kV to 35 kV tariff category in Decision No. 2892, at VND 1,814/kWh during normal hours and VND 3,348/kWh during peak hours. To isolate the impact of time-of-use classification, both scenarios use the same new tariff rates and assume consumption of 1,000 kWh.

  • Scenario A — 09:30–11:30: Under the previous schedule, this was a peak period; under Decision No. 963, it is a normal period. Hypothetical cost difference: 1,000 × (1,814 − 3,348) = −1,534,000 VND.
  • Scenario B — 20:00–22:00: Under the previous schedule, this was a normal period; under Decision No. 963, it is a peak period. Hypothetical cost difference: 1,000 × (3,348 − 1,814) = +1,534,000 VND.

These are two independent hypothetical scenarios, excluding VAT. They are not project data, electricity bill forecasts, or verified savings. Tariff rates are held constant at those prescribed by Decision No. 2892 to isolate the effect of the time-of-use schedule. This is not a comparison of bills before and after November 1, 2026.

Therefore, it would be incorrect to conclude that every factory will pay less for electricity simply because the average retail tariff has fallen by 2% or because peak hours have shifted to the evening. A proper assessment must reclassify all kilowatt-hours within the same load-profile period and compare the results using the relevant rates, contractual terms, and metering arrangements.

4. Three steps factories should take

Step 1. Confirm the tariff and metering point

Facility Management and Finance teams should review the electricity supply contract, supply voltage at the metering point, customer tariff category, latest bill, and supplier notices concerning the applicable tariffs and time-of-use schedule. Factories located in industrial parks should also identify the contractual electricity seller and the actual pricing arrangement.

Step 2. Collect interval load data

Readings at 15-minute or 30-minute intervals, or at the finest available resolution, are more informative than a single monthly kWh total. The dataset should cover production days, weekends, night shifts, and materially different operating patterns to avoid conclusions based on an unrepresentative day.

Further reading: Factory load-profile analysis: What data should you examine?

Step 3. Compare the two cost scenarios

Using the same dataset, calculate energy consumption and cost under the time-of-use schedule currently applied to the meter, then compare the results with the schedule specified in Decision No. 963. The analysis should show differences by time period, tariff assumptions, and the effects of production operations. If the supplier has not confirmed the changeover date, the new-schedule result should be treated as an analytical scenario only.

5. When should Solar PV, BESS and EMS be evaluated?

A tariff change provides a reason to review operating strategies; it is not, by itself, sufficient justification for investing in an energy storage system.

  • Adjusting operating schedules: Viable only for loads that can be shifted without compromising safety, product quality, staffing, or production deadlines.
  • Solar PV: May reduce grid electricity purchases when PV generation coincides with electricity demand. It should not be assumed to directly meet evening peak-hour demand.
  • Battery Energy Storage Systems (BESS): May support load shifting, peak shaving, or selected reliability objectives when properly configured. Feasibility depends on the load profile, intended application, power and energy sizing, control strategy, system integration, EMS, losses, lifecycle costs, and operating limits. BESS should not automatically be treated as a replacement for a UPS or as a guarantee of uninterrupted power supply.
  • Energy Management Systems (EMS): Can support monitoring, analysis, and coordinated control where the equipment, connectivity, and required functions are included in the system design. Monitoring capability does not necessarily confer the authority or technical ability to control every load automatically.

Further reading: Integrating Solar PV and BESS for factories: Designing generation, storage and loads as one system.

6. Frequently asked questions

When do the new industrial electricity tariffs take effect?

Decision No. 2892/QĐ-BCT specifies that the revised electricity tariffs apply from November 1, 2026. The rate paid by a particular factory also depends on its electricity-use category, the voltage at its metering point, and the applicable time-of-use period.

What are the new peak hours?

Decision No. 963/QĐ-BCT specifies 17:30–22:30, Monday through Saturday, as the new peak period. Businesses must nevertheless confirm when their meters are changed over before using this schedule to estimate electricity bills.

If the average retail electricity price falls by 2%, will factories save 2%?

Not necessarily. Actual electricity costs depend on the applicable customer tariff, consumption during each time-of-use period, contractual arrangements, and when the meter schedule is updated.

Will BESS definitely reduce electricity costs once peak hours move to the evening?

No. Economic performance must be assessed against the load profile, tariff differentials, charge/discharge capabilities, system losses, control strategy, operational constraints, and total lifecycle costs.

7. Checklist before making a decision

  1. Is the tariff category correct? Confirm the electricity-use purpose, supply voltage, contract, and bill.
  2. Has the meter’s time-of-use schedule been updated? Check supplier notices and the period reflected on the bill.
  3. Is interval load data available? Does it represent operating shifts, non-working days, and production variations?
  4. Have both scenarios been compared using the same dataset? Separate the effects of tariff rates, time-of-use periods, and energy consumption.
  5. Is the proposed operating solution feasible? Evaluate safety, production requirements, and lifecycle costs before selecting a technology.

Conclusion: Confirm the meter schedule before recalculating electricity costs

The revised electricity tariffs effective November 1, 2026, have been announced. To estimate costs that correspond more closely to actual billing, factories should verify the time-of-use schedule configured on their meters and reclassify consumption using interval load data. This also provides a basis for deciding whether to adjust production shifts, implement demand management, or invest in energy solutions.

365Energy approaches industrial energy challenges by first examining each factory’s load data, technical constraints, and operating requirements, before proposing an appropriate system configuration and scope of work.

Need to verify your time-of-use tariff periods, analyze factory load data, or evaluate Solar PV/BESS/EMS scenarios? Contact 365Energy to discuss an initial assessment.


References

  1. EVN – Announcement of the average retail electricity price adjustment effective November 1, 2026 (October 31, 2026).
  2. Decision No. 2892/QĐ-BCT dated October 31, 2026 – Electricity tariffs and appendix.
  3. MOIT – Decision No. 963/QĐ-BCT dated April 22, 2026.
  4. Circular No. 60/2025/TT-BCT dated December 2, 2025 – Articles 5, 20 and 21.
  5. Electricity Regulatory Authority – Document No. 1026/ĐL-TTD&HTĐ dated April 24, 2026.

Sources reviewed and content updated: November 2, 2026. This article provides policy information and an analytical framework; it does not replace confirmation from the electricity supplier or site-specific legal, technical, or financial advice. Check for subsequent amendments and the supplier’s actual implementation notices before applying these provisions.