S&J Hosiery Vietnam has officially brought its 578.5 kWp rooftop solar energy project into operation at its manufacturing facility in My Phuoc 2 Industrial Park, marking a practical step forward in integrating clean energy into textile manufacturing. Delivered by Handong 365 Energy, the system commenced commercial operations on 11 November 2026.
Advancing Onsite Renewable Energy for Industrial Facilities
Rooftop solar gives manufacturers a way to generate renewable electricity on existing factory roof space, close to where it is used. It adds an onsite energy source that can contribute to daytime electricity demand.
For industrial businesses, this gives existing roof space an additional role in the factory’s energy supply. It is a way to combine the use of available infrastructure with longer-term sustainability objectives.

Key Project Information
The project adds rooftop solar generation at S&J Hosiery Vietnam’s textile manufacturing facility. Delivery was undertaken by Handong 365 Energy, the joint venture established by Handong E&C and 365Energy.
Key project information:
- Project: S&J Hosiery Vietnam Rooftop Solar Project
- Location: My Phuoc 2 Industrial Park
- Client Sector: Textiles
- Installed Capacity: 578.5 kWp
- Commercial Operation Date (COD): 11 November 2026
- Estimated Annual Generation: 834.97 MWh/year
- Estimated Annual CO₂ Reduction: 516.60 tonnes CO₂/year
- Delivery Entity: Handong 365 Energy


Collaborative Delivery and Partnership
As an integrated energy partner for industrial and foreign-invested enterprises in Vietnam, 365Energy focuses on solutions suited to each plant’s operating needs and energy objectives. The successful commissioning of the S&J Hosiery Vietnam rooftop installation reflects the collaboration between S&J Hosiery Vietnam and the project team at Handong 365 Energy. 365Energy thanks S&J Hosiery Vietnam for its trust and partnership, and Handong E&C and the Handong 365 Energy project team for their collaboration in bringing the system into operation.

Annual generation and CO₂ reduction figures are estimates reported in the project announcement by Handong E&C.