Contact us

40 000 kWp
Total capacity58 400 Tons/year
Reduced CO2 emissionsTime: 2019
Location: Mui Ne ward, Phan Thiet city, Binh Thuan province
Mui Ne Solar Energy Plant Project, with a capacity of 40 MWp and a total investment of more than 1,000 billion VND, was developed on a 38-hectare plot of land in Mui Ne ward, Phan Thiet city (Binh Thuan).
The factory is installed with more than 100,000 solar panels with a capacity of 365W each.
The Mui Me solar Energy plant is connected to the national power system at 110kV voltage via a dual-circuit 110kV line connected to the 110kV line in Luong Son town, Bac Binh district, Mui Ne ward, Phan Thiet city, via the project’s 22/110kV transformer station.
On June 4, 2019, the project was successfully connected to the National Grid, only 8 months after construction began.